Annual Report 2025-26
The Sacramento County (“County”) Department of Transportation provides and makes available the following Fair Share Fee Program Annual Report for the Fiscal Year ending on June 30, 2026, pursuant to the requirements of the Mitigation Fee Act (California Government Code Section 66000, et seq.):
A. A brief description of the type of fee in the account or fund:
Based on traffic studies, the County may condition development projects to make proportional contributions (“fair share”) to mitigate impacts that occur off-site from the project and are not otherwise included within the project’s participating fee program(s).
Additionally, Sacramento County Code (SCC) chapter 12.03 generally requires the construction of on-site (along the adjacent county street) improvements in conjunction with any construction, grading, or related work. In certain circumstances defined in SCC 12.03, the County may accept a cash payment in lieu of improvements (“Cash In Lieu”), when it is appropriate to postpone construction of the improvements to a later time.
For those off-site or on-site improvements that are not required to be immediately constructed, the County’s Transportation Fair Share Fee Program (FSFP) collects funding to contribute toward construction. Additional funding sources may include any of the following: Sacramento County Transportation Development Fee/Transit Impact Fee (SCTDF/TIF); County Measure A Sales Tax; State Gas Tax; various Community Finance Plans; reciprocal funding from other jurisdictions; or State or Federal Funding or Grant Programs.
B. The amount of the fee:
The amount of fee charged is proportional to the project’s impact and based on the value of the associated improvement. Fees charged for FY 2025/26 include:
Fair Shares Collected
| SacDOT Log # | Date Entered | Address Location | Fair Share Amount |
|---|---|---|---|
| 420 | August 2025 | 6307 Stonehouse Rd | $53,520.00 |
| 421 | August 2025 | 6307 Stonehouse Rd | $50,266.00 |
| 422 | October 2025 | 7907 Antelope North Rd | $411,387.42 |
| 425 | April 2026 | 073-0790-044 | $61,689.50 |
| 426 | April 2026 | 2415 Ak St. | $1,600.00 |
| Total Collected FY 2025/26 | $578,462.92 |
Cash In Lieu (CIL) Collected
| SacDOT Log # | Date Entered | Address Location | Fair Share Amount |
|---|---|---|---|
| 423 | January 2026 | 8695 Greenback Ln | $3,000.000 |
| 424 | January 2026 | 3438 Watt Ave | $12,155.00 |
| Total Collected FY 2025/26 | $15,155.00 |
C. The beginning and ending balance of the account or fund (FY 2025/26):
Fair Share Fees
Beginning Fund Balance (7/1/2025): $2,053,157
Ending Fund Balance (6/30/2026):$2,734,528
Cash-In-Lieu
Beginning Fund Balance (7/1/2025): $4,130,113
Ending Fund Balance (6/30/2026): $4,326,232
D. The amount of fees collected and the interest earned (FY 2024/25):
Fair Share Fees
Amount of Fees Collected: $578,463
Interest Earned: $102,908
Cash-In-Lieu
Amount of Fees Collected: $15,155
Interest Earned: $180,963
E. An identification of each public improvement on which fees were expended and the amount of the expenditures on each improvement, including the total percentage of the cost of the public improvement that was funded with the fees:
Fair Share Expenditures
None
Cash In Lieu Expenditures
| SacDOT Log# | Date Entered | Project Name | Fair Share Amount | Project Cost | % Funded by Fees |
| 340 | Nov 2008 | Bradshaw Rd/ Jackson Rd Intersection Improvements | $398,416.82 | $3,682,000 | 10.8% |
| 385 | Sept 2016 | Florin Road Bicycle Pedestrian Improvements | $8,000.00 | $12,684,000 | 0.1% |
| Total Amount Spent: | $406,417 |
F.
i. An identification of an approximate date by which the construction of the public improvement will commence if the local agency determines that sufficient funds have been collected to complete financing on an incomplete public improvement, as identified in paragraph (2) of subdivision (a) of Section 66001, and the public improvement remains incomplete.
Sufficient funding has been collected for the following projects, with the following funding sources and anticipated start dates:.
| Project | Estimated Construction Start | Funding Sources1 |
| Bradshaw Road at Ballinger Drive Traffic Signal | April 2028 | FSFP, developer funds |
| Bradshaw Road at Jackson Road Intersection Improvements | April 2028 | CIL, SACOG Transformative program, STIP |
| Florin Road Bicycle Pedestrian Improvements | December 2024 (construction ongoing) | CIL, HSIP, ARPA, CDBG |
| Eschinger Road Improvements | March 2027 | FSFP, SCTDF/TIF |
| Fair Oaks Boulevard Bicycle & Pedestrian Mobility Project – Phase 2 | July 2026 (construction ongoing) | FSFP, CMAQ, interagency agreements |
1 The following is a list of abbreviations:
ARPA = American Rescue Plan Act
CDBG = Community Development Block Grant
CIL = cash-in-lieu
CMAQ = Congestion Mitigation and Air Quality
FSFP = fair share fee program
HSIP = Highway Safety Improvement Program
SACOG = Sacramento Area Council of Governments
SCTDF/TIF = Sacramento County Transportation Development Fee/Transit Impact Fee
STIP = State Transportation Improvement Program
It has been determined that the current fund balance is insufficient to initiate construction on the remaining public improvement projects. The County will continue to allocate funds to these projects as they become available.
ii. An identification of each public improvement identified in a previous report pursuant to clause (i) and whether construction began on the approximate date noted in the previous report.
| Project | Has Construction Commenced? |
| Bradshaw Road at Ballinger Drive Traffic Signal | No |
| Bradshaw Road at Jackson Road Intersection Improvements | No |
| Florin Road Bicycle Pedestrian Improvements | Yes |
| Eschinger Road Improvements | No |
| Fair Oaks Boulevard Bicycle & Pedestrian Mobility Project – Phase 2 | Yes |
iii. For a project identified pursuant to clause (ii) for which construction did not commence by the approximate date provided in the previous report, the reason for the delay and a revised approximate date that the local agency will commence construction.
| Project | Previous Approx. Date | Revised Approx. Date | Reason for Delay |
| Bradshaw Road at Ballinger Drive Traffic Signal | April 2027 | April 2028 | Longer than anticipated time for surveying |
| Bradshaw Road at Jackson Road Intersection Improvements | April 2027 | April 2028 | Longer than anticipated time for outside agency reviews |
| Eschinger Road Improvements | April 2026 | March 2027 | Longer than anticipated time for right of way acquisition |
G. A description of each interfund transfer or loan made from the account or fund, including the public improvement on which the transferred or loaned fees will be expended, and, in the case of an interfund loan, the date on which the loan will be repaid, and the rate of interest that the account or fund will receive on the loan:
None
H. The amount of refunds made pursuant to subdivision (e) of Section 66001, the number of persons or entities identified to receive those refunds, and any allocations pursuant to subdivision (f) of Section 66001:
None