Sunrise Boulevard Wall Replacement Project

Background

SacDOT is replacing a portion of the soundwall along southbound Sunrise Boulevard after inspections uncovered a portion of the soundwall along the road is beginning to fail. SacDOT inspectors noticed the wall was buckling and leaning toward the roadway.

SacDOT immediately addressed this issue by closing the sidewalk and vehicle travel lane next to the soundwall.  SacDOT is moving forward with replacement of the soundwall this summer..

Lane Closure

June 9, 2026 to September 2026

The lane closure will be the #3 southbound lane (next to the sidewalk) on Sunrise Blvd between Wildridge Drive and Sunset Avenue. The lane closure signage will stretch north of Madison Ave into the City of Citrus Heights.

Sunrise Blvd Wall Project Location

Project Work Includes

  • Removal and replacement of 2 failing soundwall sections
  • Sidewalk replacement
  • Streetlight replacement
  • Tree removal
     

Project Funding

The reconstruction cost is $1,392,853.75.  Funding for the project is provided by County Road Fund.

Contact Information

Spencer Ord, Senior Civil Engineer
Sacramento County Department of Transportation
E-mail: OrdS@saccounty.gov
Phone: (916) 876-6601

Clara Ledesma, Resident Engineer
Sacramento County Construction Management and
Inspection Division
E-mail: ledesmac@saccounty.gov
Phone: (916) 874-5273