AC Overlay Project 2026 Phase A
1,3,4
Place conventional asphalt concrete, rubberized asphalt concrete, rubberized cape seal or slurry seal over the existing pavement; ADA compliant upgrades; Replace damaged culverts. Construction activities will include base repair, raising manholes, and grinding existing pavement prior to paving.
Daniel Lockett
01/26 (B) Jan-26
Jun-26
Nov-26
$14,000
Elkhorn Blvd - 26th Ave to 32nd St
 
Walerga Rd - Don Julio Blvd to Elkhorn Rd
Madison Ave - Kenneth Ave to Hazel Ave
Sunrise Blvd - Sunset Ave to Sunrise Ridge Dr
Oak Ave - Chestnut Ave to Santa Juanita Ave
Antelope Rd - Walerga Rd to Elverta Rd
Watt Ave - El Camino Ave to Marconi Ave
Walerga Rd - Elkhorn Blvd to Antelope Rd
6411 Grant Ave - Culvert Replacement Only