Fair Oaks Blvd Bike Pedestrian Mobility Project Phase 2
Project Master List
| Project Name & Locations | Supv. Distr. | Project Description | Project Engineer | Plans Sent to Utilities | Board Approval | Construction Starts | Construction Complete | Contract Amount ($K) |
| Fair Oaks Blvd: Howe Ave to Munroe St | 3 | Create a smart growth corridor with barrier separated bicycle lanes, and improved pedestrian access. Resurface roadway and install landscaping, shade trees, and street lighting. New traffic signals at University Ave/FOB and Fulton Ave/FOB. Signal modifications at Sierra Blvd/FOB. | David Markowski | 06/25 (C) | Jan-26 | Jul-26 | Jul-27 | $10,200 Federal (CMAQ, RSTP) |