Project Master List

Folsom Blvd Complete Streets Improvements Phase 2

Project Name & Locations Supv. Distr. Project Description
Project Engineer Plans Sent to Utilities
Board Approval Construction Starts Construction Complete Contract Amount ($K)
Folsom Blvd: Starfire Dr to Mayhew Rd
3,5
Install bike lanes, sidewalks, street lights, landscaping, fencing, ADA ramp and signal upgrades at La Riviera Dr, Tiber Dr, and Mayhew Rd.
Anthony Voo
08/21 (A) Dec-26
Mar-27

Nov-27

$6,000

Local Funds