The proposed project is the next critical step of improvements proposed for the South Watt Ave. corridor between Florin Rd. and Jackson Rd. (State Route-16), increasing the capacity of the road way from a two-lane facility to a four-lane facility with bicycle, pedestrian, and transit accommodations. The ultimate configuration of the corridor will incorporate additional capacity improvements, widening the four-lane facility to a six-lane road way with similar multimodal accommodations.
The proposed 3-mile long project will:
The purpose of the South Watt Ave. Improvement Project is to:
Monday, March 23, 2026 to Friday, March 27.
Intersection of South Watt Avenue and Fruitridge Road
7:00pm to 6:00am
South Watt Avenue Improvement Project Report
Preliminary Design: 2018-2020
Final Design: 2021 - 2024
Right of Way Acquisition: 2021 - 2024
Construction: 2025-2026
Keith Gotwalt, Senior Civil Engineer
(916) 874-2818