Project Description
This project will widen Bradshaw Road and Jackson Road to include an additional lane and dual lefts in each direction. This project will also include modifications to the traffic signal.
Tentative Schedule
- Preliminary Engineering:2024
- Environmental Clearance: 2025
- Design: 2025 to 2026
- Right-of-Way Acquisition: 2025 to 2026
- Construction: 2027
Funding
Estimated total project costs are $3,645,000 and will be provided by Measure A and Developer Fee Funding
Contact Information
Jenny Singh, Senior Civil Engineer
Phone: 916-874-6092
Email: singhje@saccounty.net
David Markowski, Associate Civil Engineer
Phone : 916-875-4736
Email: Markowskid@saccounty.gov